Ethiopia has requested assistance from Norway to carry out studies of two multipurpose projects on the Abay River (the Blue Nile within Ethiopia, the largest tributary to the Nile River), namely the Mandaya and Beko- Abo Multipurpose projects.
Client: Ministry of Water and Energy (MoWE); – formerly Ministry of Water Resources.
NVE Mandate: Advisory services to executing agency MoWE on: i) Implementation of two feasibility studies, and; ii) Preparation of project document for Capacity Building in collaboration with MoWE.
Contract Value/ Duration: MNOK 4.500 from Norad; started (formally) November 2009 and lasting until 2010/11
Type of Activities: Workshops, seminars, site visits, preparation of documents, procurement, advisory services, sub-consultant to Eastern Nile Technical Regional Office (ENTRO).
Work Completed 2010: Procurement of technical consultants; procurement of environmental consultants; Preparation of project document and contract for institutional cooperation between MoWE and NVE.
Work in Progress 2010: Assistance to MoWE in procurement of panels of experts for dam safety and environment and social aspects for the feasibility studies.
Activities and Outputs:In the short time since the project became fully active, the efforts have mostly entailed different preparatory tasks. The tender process for the feasibility studies for the Mandaya and Beko Abo projects was initiated in autumn 2009. The current status is::
Results/Outcome:Several positive results/outcomes have materialized during 2010. The most important ones are: